November 11th. Excavation is basically done

10 Likes

November 16th
20201116_170301 20201116_170413

6 Likes

Un message a été fusionné à un sujet existant : Solstice - 44 étages

Ils utilisent la même machine qu’au Solstice pour sortir les dernières pelletés

1 Like

December 2nd. Work on what is going to be the elevator cage and the core is getting done. Hopefully we can see the crane up before the holidays.

20201202_172953

6 Likes

December 8th

7 Likes

December 14th. Not much progress this week.

4 Likes

January 26th. Difficult to see, but work is getting done on what seems to be the future elevator pit.

4 Likes

Crane installed late last night.

10 Likes

February 7th. Still working on adding the weights to the crane.

9 Likes

Montreal crane :building_construction: city …

1 Like

(long-time lurker, first time poster)

Crane is up and operational.

29 Likes

Bienvenue !

C’est depuis la TDC 2?

1 Like

Bienvenue et merci pour le super point de vue!

Merci à vous!
Oui, c’est vu de la TDC2.

2 Likes

Welcome to the club, and what a great first picture! If you live @TDC2, you will have a great perspective to provide us updates on these two projects. :smile:

3 Likes

15 février. J’aurais pu mettre ce combat de grues dans plusieurs fils :stuck_out_tongue:

9 Likes

Je remarque que presque tous les étages de l’Avenue ont des lumières, c’est bon signe!

2 Likes

Like Detroit did for the Super Bowl in 2006! :grin:

Village Potemkine

February 18th. I think only @FrancoisL will be able to give us good updates of this site until it reaches ground floor.

7 Likes